This project was developed from the design phase in partnership with engineering firm ARRAM. Within three weeks, 20 axes were milled, a copper mesh was laid, several copper protection layers were applied, and the DURALIT flooring was installed.
The goal was to enable the entry of a 400-ton transformer into the area just 72 hours after completion, while fully complying with AEROGO’s stringent technical requirements. A remarkable achievement for such a complex challenge.